Primavera System :
SureTrak Video : How To Add a New Activity in PERT View
No Need to register just click and get started ...
How To
Step #1: Click on the PERT button.
Step #2: Select an activity block.
Step #3: Type a name for the new activity in the Activity Form.
Step #4: Click OK.
Step #5: Click Close.
Step #6: Click on the Bar Chart button.
Result: A new activity has been added in PERT view.
Step #2: Select an activity block.
Step #3: Type a name for the new activity in the Activity Form.
Step #4: Click OK.
Step #5: Click Close.
Step #6: Click on the Bar Chart button.
Result: A new activity has been added in PERT view.
Quick Step
PERT button
More Information
This action allows the user to add an activity to the project and use PERT to review its logical flow as well.
Keep Visiting for more tutorials of new software's...